According to the ship prying block type superstructure and the construction method, the cover plate is segmented and divided into the superstructure for construction, so that more equipment installation and debugging tests are carried out in advance to a platform stage and are carried out in parallel with main ship body operation, and before hoisting, equipment such as ship electromechanical outfitting equipment is installed to 100% at the platform stage, so that the ship prying block type superstructure is constructed. And 95% debugging and checking operations and the like are carried out on the platform, so that the workload is advanced. After the construction method is implemented, in the dock stage, after the superstructure is hoisted in place, the purpose of plug-and-test can be achieved by the ship and the machine, and the superstructure is changed to be '0' before docking, so that pre-embedded equipment such as a cabin main engine can be ensured to be installed in place according to a plan, and the continuous input amount of the dock for superstructure operation is greatly reduced; and the dock wharf period is shortened, the construction efficiency is greatly improved, and the popularization value is high.
本发明提供一种船舶撬块式上层建筑及建造方法,该建造方法将盖板分段划分至上层建筑进行建造,使得更多的设备安装及调试试验提前至平台阶段进行,并与主船体作业是并行作业,在吊装前,在平台阶段就将船机电舾等设备安装到100%,并在平台上进行95%的调试报验等作业,作业量提前。这种建造方法实施后,等到船坞阶段,将上层建筑吊装到位后船机电即可达到即插即试的目的和进坞前上层建筑“0”改单,不仅可以保证机舱主机等预埋设备按计划安装到位,大幅度减少码头船坞对上层建筑作业的持续投入量,且缩短了船坞码头周期,大幅度提高了建造效率,推广价值高。
Ship prying block type superstructure and construction method
一种船舶撬块式上层建筑及建造方法
2024-07-19
Patent
Electronic Resource
Chinese
IPC: | B63B Schiffe oder sonstige Wasserfahrzeuge , SHIPS OR OTHER WATERBORNE VESSELS |
Overall construction method for ultra-large type superstructure block
European Patent Office | 2020
|