The invention provides a wharf breakwater engineering accropode installation process, and belongs to the field of wharf breakwater construction, and the wharf breakwater engineering accropode installation process comprises the following steps: S1, construction preparation; s2, formwork manufacturing and formwork erecting are conducted, specifically, the accropode formwork is designed in a vertical erecting mode, and three-transverse vertical prefabrication is adopted during prefabrication; s3, concrete pouring and formwork removal are conducted, specifically, the concrete is poured in a layered mode and vibrated, and formwork removal work is conducted after the initial setting strength of the concrete meets the requirement; s4, block maintenance and storage; s5, drawing a block placement graph; s6, the accropode is transported, specifically, according to the placement plan of the accropode, the accropode is transported to a prefabricated yard shipping wharf from the stacking area, then the accropode is transported to the accropode placement area to be stopped, and the accropode is placed and constructed through a crane ship; s7, placing the accropode block on water; during water accropode placement construction, the accropode is randomly placed by a crane ship according to 95% of the design number of the accropode, then inspection or leak repairing is carried out, and the installation process can shorten the construction period and reduce the construction cost.

    本发明提供一种码头防波堤工程扭王块安装工艺,属于码头防波堤施工领域,包括如下步骤:S1:施工准备;S2:模板制作及模板支立:扭王字块模板采用立式支立设计,预制时采取“三横”立式预制;S3:浇筑混凝土及拆模:混凝土采用分层浇注并振捣,待混凝土初凝强度达到要求后进行模板拆除工作;S4:块体养护与贮存;S5:块体安放图绘制;S6:扭王字块的出运:根据块体的安放计划,将块体自堆放区运输块体到预制场出运码头,然后运至块体安放区停靠并由起重船进行安放施工;S7:扭王字块体水上安放;水上扭王字块安放施工先由起重船按设计块数的95%定计算网点的位置随机安放,完成后再进行检查或补漏,本安装工艺可缩短施工周期,降低施工成本。


    Zugriff

    Download


    Exportieren, teilen und zitieren



    Titel :

    Wharf breakwater engineering accropode installation process


    Weitere Titelangaben:

    一种码头防波堤工程扭王块安装工艺


    Beteiligte:
    LIU CHAO (Autor:in) / KONG CHUNYAN (Autor:in) / WANG WEI (Autor:in) / ZHOU LIN (Autor:in) / KO DONG-HOON (Autor:in) / SUN XIANGKAI (Autor:in) / LIU RISHANG (Autor:in) / LU SHAN (Autor:in) / WANG YUTING (Autor:in)

    Erscheinungsdatum :

    13.08.2024


    Medientyp :

    Patent


    Format :

    Elektronische Ressource


    Sprache :

    Chinesisch


    Klassifikation :

    IPC:    B66C Krane , CRANES / E02B HYDRAULIC ENGINEERING , Wasserbau / B28B Formgeben von Ton oder anderen keramischen Stoffzusammensetzungen, Schlacke oder von Mischungen, die zementartiges Material enthalten, z.B. Putzmörtel , SHAPING CLAY OR OTHER CERAMIC COMPOSITIONS, SLAG OR MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER





    Accropode lifting appliance and lifting method

    GAO DEFENG / SHENG ZHIGANG / QIAN WANGFENG et al. | Europäisches Patentamt | 2024

    Freier Zugriff

    Accropode lifting appliance and lifting method

    FANG CHENGSHI / LI LIUHUAN / SUN WEIZHONG et al. | Europäisches Patentamt | 2025

    Freier Zugriff

    Fisherman's Wharf Breakwater Monitoring Study, San Francisco, California

    Lott, Jonathan W. | HENRY – Bundesanstalt für Wasserbau (BAW) | 1994

    Freier Zugriff