The report discusses the various types of changes the Navy makes to shipbuilding contracts, the cost impact of the changes, how the changes are used a a basis for contractors to file claims against the Government, and some of the action being taken by the Navy to minimize changes and resulting claims. The review was made to find out how the Navy processes contract changes and whether the changes are necessary.