The invention provides an assembly type alum storage tank construction method which comprises the following steps: S1, constructing a bottom cushion layer of a tank, and reserving wall plate supporting embedded ribs; s2, paying-off positioning is carried out, the prefabricated wallboards are hoisted in place, and the prefabricated wallboards and the wallboard supporting embedded ribs are fixed; s3, steel bars and formworks at the connecting joints of the prefabricated wallboards and the constructional columns are installed; s4, bottom plate upper-layer steel bars and a formwork are installed, bottom plate concrete pouring is conducted, and the bottom plate and the prefabricated wall plate are connected into a whole in a pouring mode; and S5, hoisting of the laminated slab and pouring of a top plate are conducted. The cushion layer is constructed, the wallboard supporting embedded ribs are reserved on the cushion layer, the splicing scheme is optimized, the prefabricated wallboards and the bottom plate are poured into a whole in a pouring mode, the construction requirement of the large alum storage pool is met, and the construction efficiency is greatly improved.

    本发明提供一种装配式贮矾池施工方法,包括:步骤S1,施工池底垫层,并预留墙板支撑预埋筋;步骤S2,进行放线定位,将预制墙板吊装就位,并将预制墙板与墙板支撑预埋筋进行固定;步骤S3,安装预制墙板连接节点处及构造柱的钢筋及模板;步骤S4,安装底板上层钢筋和模板,进行底板混凝土浇筑,将底板与预制墙板通过浇筑的形式连接为整体;步骤S5,进行叠合板的吊装和顶板浇筑。施工垫层并在垫层上预留墙板支撑预埋筋,优化拼装方案,通过浇筑的形式将预制墙板与底板浇筑为一体,满足大型贮矾池的施工要求,大大提高了施工效率。


    Access

    Download


    Export, share and cite



    Title :

    Fabricated alum storage pool construction method


    Additional title:

    一种装配式贮矾池施工方法


    Contributors:
    HUO HUIFENG (author) / DUAN HANTAO (author) / ZHANG JIANGHUA (author) / PENG LULEI (author) / XU HONGBIN (author) / ZHANG KAI (author) / XU JUN (author) / KUANG AO (author) / DUAN CHENCHEN (author) / LIU WEI (author)

    Publication date :

    2023-12-29


    Type of media :

    Patent


    Type of material :

    Electronic Resource


    Language :

    Chinese


    Classification :

    IPC:    E04H Gebäude oder ähnliche Bauwerke für besondere Zwecke , BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES / B66C Krane , CRANES / E04B Allgemeine Baukonstruktionen , GENERAL BUILDING CONSTRUCTIONS / E04G SCAFFOLDING , Baugerüste



    Spillway for Alum Creek Dam, Alum Creek, Ohio: Hydraulic Model Investigation

    Pickering, Glenn A. | HENRY – Federal Waterways Engineering and Research Institute (BAW) | 1970

    Free access


    Spacex alum goes after falcon 1 market

    Morring Jr., Frank | Online Contents | 2014


    FPSO moon pool structure construction method

    MEI ZHONGHUA / HONG CHANGSHENG / WANG YONGQIANG et al. | European Patent Office | 2023

    Free access

    Car washing pool and sedimentation pool device for construction site and construction method thereof

    XIAO PEILEI / LIU YUTAO / ZHAO SHUSHAN et al. | European Patent Office | 2021

    Free access