The project involves the following: Construct new runway 3/21 (6600 feet x 150 feet) and associated taxiways; construct parallel taxiway to runway 10/28; relocate communication towers; install homer beacon for runway 10/28; construct and equip crash, fire, and rescue facility; acquire land for runway 3/21 and for extension of runway 10/28. An expected impact is more frequent use of airport by jet aircraft with the resultant increase in noise and air pollution in the approach areas. All environmental impact is expected to be within tolerable limits. (Author)
Lafayette Airport, Lafayette, Louisiana
1971
21 pages
Report
Keine Angabe
Englisch
Lafayette Airport, Lafayette, Louisiana