Analysis of the PAC-3 missile development progress currently indicates the first missile flight test will occur in Jun 97. An assessment of the requisite program activities is ongoing to determine potential impacts to the remaining schedule. Overall, the program continues to be on track to achieving all parameters established by the 20 Aug 96 approved Acquisition Program Baseline.