The National Aeronautics and Space Administration (NASA) spends 90 percent-$13 billion-of its budget on contractors. Yet since 1990, GAO has designated NASA's contract management as a high-risk area-in part because the agency failed to implement a financial management system to provide information needed to make key program decisions. In April 2000, NASA initiated its most recent effort to implement an effective financial management system-the Integrated Financial Management Program (IFMP). Three years into the program, GAO found NASA risks building a system that will cost more and do less than planned. As a result, the Congress requested reviews of NASA's IFMP enterprise architecture and financial reporting and program cost and schedule controls.