Progress on the building of AGOR 28, oceanographic research vessel Sally Ride. Work continues 1) reviewing Vendor Recommended Spares (VRS); 2) reviewing Technical Manuals and Supplemental Information; 3) work on initial outfitting lists for Sally Ride; and working on NS5 Hierarchy. Intermediate Shaft Bearings have been installed on Ride s modified foundations. Alignment in progress on both vessels. Unresolved issues with fairlead interferences from TK70-70 main crane remain. DCI is using Sally Ride's aft fairlead foundation to test various new locations on Armstrong.