The Navys 2018 Shipyard Infrastructure Optimization Plan includes actions to address critical deficiencies at the shipyards, but the extent to which the plan fully addresses those deficiencies remains to be seen as the proposed actions arecomplex and years away from being implemented. The plan includes steps to address dry dock deficiencies, which the Navy expects will provide it with the capacity and capability to perform 67 of 68 ship maintenance periods it is currently unable to support through fiscal year 2040. Once area development plans are complete (see figure), the Navy projects it will take at least $21 billionover 20 years to fully implement the plan.