The invention discloses high-rise building curtain wall annular double-track hoisting equipment and a using method thereof.The high-rise building curtain wall annular double-track hoisting equipment comprises a plurality of supporting structures, outer annular tracks and inner annular tracks are arranged at the bottoms of the supporting structures, and the inner annular tracks are arranged on the inner sides of the outer annular tracks. The lifting structure in the hanging basket mechanism can move bidirectionally, and after the first electric hoist moves the hanging basket mechanism to the position near a construction point, a lower sliding plate in the lifting structure can move a rod, so that the position of a hanging basket main body is finely adjusted towards a building body or away from the building body; meanwhile, the position of the hanging basket body can be finely adjusted in the two-side direction through movement of the upper sliding plate, and the position of the hanging basket can be adjusted more conveniently; when the curtain wall unit plate is installed, bidirectional movement of the curtain wall unit plate can be achieved through the two sliding grooves at the position of the rotating rod of the handheld column, the inclination angle of the curtain wall unit plate can be adjusted through rotation of the rotating rod, alignment is more accurate, the position of the curtain wall unit plate does not depend on manual adjustment of constructors, and construction is easier and more convenient.

    本发明公开了一种高层建筑幕墙环形双轨吊装设备及其使用方法,包括多个支撑结构,多个所述支撑结构底部设置有外环轨及内环轨,所述内环轨设置在外环轨内侧。本发明吊篮机构中吊起结构可以进行双向的移动,在第一电动葫芦将吊篮机构移动至施工点附近后,吊起结构中的下滑移板可以进行移动杆,使得吊篮主体位置朝着楼体或与远离楼体的方向微调,同时上滑移板的移动可以使得吊篮主体位置进行两侧方向的微调,更加便于调整吊篮的位置;在进行幕墙单元板安装时,手扶柱转杆处,通过两个滑槽可以实现幕墙单元板的双向移动,并且通过转杆的转动,可以调整幕墙单元板倾斜的角度,对位更加精准,不依赖施工人员手动调整幕墙单元板的位置,施工更加简便。


    Zugriff

    Download


    Exportieren, teilen und zitieren



    Titel :

    Annular double-track hoisting equipment for high-rise building curtain wall and using method thereof


    Weitere Titelangaben:

    一种高层建筑幕墙环形双轨吊装设备及其使用方法


    Beteiligte:
    YANG GANG (Autor:in) / ZHANG ZHONGYANG (Autor:in) / LIU ZHAOYONG (Autor:in) / TAN CHUNLING (Autor:in)

    Erscheinungsdatum :

    26.11.2024


    Medientyp :

    Patent


    Format :

    Elektronische Ressource


    Sprache :

    Chinesisch


    Klassifikation :

    IPC:    B66C Krane , CRANES / E04G SCAFFOLDING , Baugerüste



    Annular double-track hoisting equipment for glass curtain wall

    LI XIAOYU / XIONG ZONGCI / SONG ZHEN et al. | Europäisches Patentamt | 2021

    Freier Zugriff

    High-rise building glass curtain wall hoisting equipment and hoisting method thereof

    WANG BAIZHANG / SU GANG | Europäisches Patentamt | 2020

    Freier Zugriff

    Curtain wall circular track adjustable hoisting equipment of high-rise building and construction method

    ZHU GUOJUN / BIAN DAFENG / WU KEXUAN et al. | Europäisches Patentamt | 2024

    Freier Zugriff

    Curtain wall traction type circular track hoisting equipment of high-rise building and construction method

    WENG GONGWEI / LIU ZHEN / JIANG XIKE et al. | Europäisches Patentamt | 2024

    Freier Zugriff

    Unit type curtain wall annular track hoisting device and design method thereof

    LIN SHAN / CAI NA / LI FUKUN et al. | Europäisches Patentamt | 2024

    Freier Zugriff