The invention relates to a hoisting system for nuclear power project nuclear island construction, which is used for continuously arranging a plurality of nuclear power units along a straight line for construction, and is characterized by comprising a guide rail, the guide rail comprises a plurality of construction guide rail groups, the construction guide rail groups are used for being arranged perpendicular to the central line of a nuclear island, and one end of each construction guide rail group extends to a construction area of the unit; one end of each construction guide rail set is used for being connected with a crane, the other end of each construction guide rail set is used for extending to the outer side of a construction area of the unit, the parts, extending to the outer side of the construction area of the unit, of the construction guide rail sets are connected through transition guide rail sets perpendicular to the construction guide rail sets, and steering gantry cranes are arranged on the guide rails.
本发明涉及一种用于核电工程核岛施工的起吊系统,用于沿直线连续布置多个核电机组进行施工,其特征在于,包括导轨,导轨包括多个施工导轨组,施工导轨组用于垂直于核岛中心线布置且施工导轨组的一端用于延伸至机组的施工区域,另一端用于伸出至机组的施工区域外侧,多个施工导轨组伸出至机组施工区域外侧的部分通过与施工导轨组相垂直的转场导轨组连接,导轨上设置有转向龙门吊,采用本发明的起吊系统克服了使用履带吊的缺陷。
Hoisting system for nuclear island construction of nuclear power engineering
一种用于核电工程核岛施工的起吊系统
01.09.2023
Patent
Elektronische Ressource
Chinesisch
IPC: | B66C Krane , CRANES |
Nuclear power station conventional island generator stator hoisting system
Europäisches Patentamt | 2022
|HOISTING METHOD FOR NUCLEAR ISLAND MAIN SYSTEM DEVICE
Europäisches Patentamt | 2023
|Europäisches Patentamt | 2021
|Nuclear power station generator stator hoisting framework system
Europäisches Patentamt | 2021
|