The invention relates to the field of steel structure truss roof construction, and discloses a large-span triangular truss air rotation lifting construction method which comprises the specific steps that construction preparation is conducted; measuring, setting out, marking and positioning; assembling a jig frame; splicing the lifting frame; assembling a roof truss; lifting the roof (turning in the air); mounting an inlaying area; and unloading the lifting frame. The problem that the truss hoisting space and the truss lifting space are not enough can be solved, and the construction efficiency can be improved.
本发明涉及钢结构桁架屋面施工领域,公开了一种大跨三角桁架空中转体提升施工方法,具体步骤包括:施工准备;测量放线,标记定位;胎架拼装;提升架拼装;屋盖桁架拼装;屋盖提升(空中转体);嵌补区安装;提升架卸载。本发明能解决桁架吊装空间及桁架提升空间不够的问题,有利于提升施工效率。
Large-span triangular truss aerial rotation lifting construction method
一种大跨三角桁架空中转体提升施工方法
2022-05-06
Patent
Elektronische Ressource
Chinesisch
IPC: | E04G SCAFFOLDING , Baugerüste / B66C Krane , CRANES / G01C Messen von Entfernungen, Höhen, Neigungen oder Richtungen , MEASURING DISTANCES, LEVELS OR BEARINGS / G01N Untersuchen oder Analysieren von Stoffen durch Bestimmen ihrer chemischen oder physikalischen Eigenschaften , INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES |
Sliding lifting method of large-span pipe truss structure
Europäisches Patentamt | 2020
|Europäisches Patentamt | 2024
|