The invention discloses a construction method for a cable-beam-free section in a tower area of a superposed beam cable-stayed bridge. The construction method comprises the following steps of: 1, mounting a temporary cantilever hanging bracket; 2, mounting a middle beam section; 3, mounting a side span first beam section; 4, temporarily fixing the side span first beam section; 5, mounting a first main span beam section; 6, temporarily fixing the main span first beam section; 7, dismantling the temporary cantilever hanger and the temporary cable. The mode that a temporary cantilever hanging bracket, a temporary cable and a tower crane on a tower body bearing platform are combined and matched is utilized, no cable beam section exists in the hoisting tower area, a floating crane is not used, and an assembling support is not arranged; therefore, the method does not occupy a main channel, reduces the construction cost, prolongs the construction period and is low in safety risk.

    本发明公开了一种叠合梁斜拉桥塔区无索梁段施工方法,包括步骤:一、临时悬臂吊架的安装;二、中间梁段的安装;三、边跨一号梁段的安装;四、边跨一号梁段的临时固定;五、主跨一号梁段的安装;六、主跨一号梁段的临时固定;七、临时悬臂吊架和临时索的拆除。本发明利用临时悬臂吊架、临时索和塔体承台上的塔吊结合配合的方式吊装塔区无索梁段,不使用浮吊,不下设拼装支架,不占用主航道、减少施工成本、提高工期,安全风险低。


    Zugriff

    Download


    Exportieren, teilen und zitieren



    Titel :

    Construction method for cable-beam-free section of superposed beam cable-stayed bridge tower area


    Weitere Titelangaben:

    一种叠合梁斜拉桥塔区无索梁段施工方法


    Beteiligte:
    WANG MINZHE (Autor:in) / NI YINSHENG (Autor:in) / KANG XIAOLONG (Autor:in) / DING WENBIN (Autor:in) / LI ZHAO (Autor:in) / HE SHENGPENG (Autor:in) / CHEN NA (Autor:in) / QU QINGLONG (Autor:in) / ZHAO YONGLI (Autor:in) / YANG SHENGXIN (Autor:in)

    Erscheinungsdatum :

    2021-11-30


    Medientyp :

    Patent


    Format :

    Elektronische Ressource


    Sprache :

    Chinesisch


    Klassifikation :

    IPC:    E01D BRIDGES , Brücken / B66C Krane , CRANES



    Bridge deck crane combined hoisting construction device for closure section of reinforced concrete superposed beam cable-stayed bridge

    ZHAO JIANGANG / LI MAOXING / JIN DONGHUA et al. | Europäisches Patentamt | 2021

    Freier Zugriff


    Cable crane bearing cable beam end self-anchoring structure of hybrid composite beam cable-stayed bridge

    ZHANG SILIANG / YU HONGZHI / YANG QINGPING et al. | Europäisches Patentamt | 2022

    Freier Zugriff

    Tower crane with cable-stayed suspension cable

    JIAO GUANGLI | Europäisches Patentamt | 2022

    Freier Zugriff

    Cable-stayed bridge main tower steel section transverse splicing installation device and method

    ZHONG RENLIANG / ZHANG QUN / YANG CHENG et al. | Europäisches Patentamt | 2022

    Freier Zugriff