With regards to technical performance, the project is running according to plan. An increase in total cost outlay was required. The new Dornier Systems schedule projects ROSAT launch readiness for April 27, 1988. However, as a result of the Challenger accident, no binding launch date has been received from NASA. The thirteenth status review was conducted at the prime contractor in March, 1986. Assembly of the FM mirror system has been interrupted due to irregularities in the gold damping; in addition, mission operation and simulator development are effected by understaffing. Postponements have been announced in the data transmission and components acquisition subsystems.