The invention discloses a ship lashing bridge building method and a ship. The ship lashing bridge building method comprises the following steps that each truss of lashing bridge is divided into a plurality of segments to be built; dividing each segment into a plurality of parts for construction; outfitting parts are installed during component construction; the components are grouped, outfitting parts are installed completely, and a complete binding bridge segment is formed; the lashing bridge segments are coated, and construction of lashing bridge marking paint is completed in a coating storage yard; laying a lashing bridge general assembly jig frame, marking a positioning line and a positioning backer on the general assembly jig frame, and turning over, positioning and general assembly the lashing bridge; the total assembling and welding work of the lashing bridge is completed; fitting-out parts and paint at the welding seam of the general assembly of the binding bridge are completed; and the binding bridge lower opening part constraint horse plate and the connecting channel steel near the platform are dismantled in advance, the binding bridge is not carried by a hanging ring, and construction of the binding bridge is completed. By adopting the method provided by the invention to construct the lashing bridge, the integrity carrying of the lashing bridge can be ensured, and the workload of a dock and the high-altitude operation risk are reduced.

    本发明公开了一种船舶绑扎桥建造方法和船舶,该方法包括以下步骤:将每榀绑扎桥分成若干个片段进行建造;将每个片段分成若干个部件进行建造;在部件建造时进行舾装件安装;进行部件大组,并将舾装件安装完整,形成完整的绑扎桥片段;将绑扎桥片段进行涂装,并在涂装堆场完成绑扎桥标记漆的施工;铺设绑扎桥总组胎架,并在总组胎架上划定位线及定位靠山,将绑扎桥进行翻身定位及总组;完成绑扎桥的总组焊接工作;绑扎桥总组焊缝处舾装件及油漆完工;提前将绑扎桥下口部分约束马板及平台附近处连接槽钢拆除,绑扎桥无吊环搭载,完成绑扎桥的建造。采用本发明提供的方法建造绑扎桥,能够确保绑扎桥的完整性搭载,减少船坞的工作量以及高空作业风险。


    Zugriff

    Download


    Exportieren, teilen und zitieren



    Titel :

    Ship lashing bridge construction method and ship


    Weitere Titelangaben:

    一种船舶绑扎桥建造方法和船舶


    Beteiligte:
    GAN JIANXIN (Autor:in) / RAN JIANHUA (Autor:in) / TONG YU (Autor:in) / XI MENG (Autor:in) / DAI WEI (Autor:in) / XIAO JINWEI (Autor:in) / YANG WENQI (Autor:in)

    Erscheinungsdatum :

    2024-05-07


    Medientyp :

    Patent


    Format :

    Elektronische Ressource


    Sprache :

    Chinesisch


    Klassifikation :

    IPC:    B63B Schiffe oder sonstige Wasserfahrzeuge , SHIPS OR OTHER WATERBORNE VESSELS



    Container ship lashing bridge integrity construction method and ship

    TAO BOZHENG / SONG KAILEI / ZHAO MING et al. | Europäisches Patentamt | 2023

    Freier Zugriff

    Lashing bridge for container ship

    Europäisches Patentamt | 2017

    Freier Zugriff

    Lashing bridge for container ship

    Europäisches Patentamt | 2017

    Freier Zugriff

    Lashing bridge for container ship

    Europäisches Patentamt | 2018

    Freier Zugriff

    LASHING BRIDGE FOR CONTAINER SHIP

    KIM SEONG AH | Europäisches Patentamt | 2015

    Freier Zugriff